|
Home Page
Main Deck
Info
What's New
Ships Log
NESF's
Background
Restoration
Education
Tour
Kids Deck
Gift Locker
Join
|
|
Structure renewal
Week ending January 10, 1997
- Two
bulkheads
running across the hull at frames 24 and 78 removed
(Quiz - D2).
Replacements laid out but not yet "hung" or installed.
- Bulkhead at frame 64, from the port
side through the centerline to the starboard side, hung and
50 percent completed.
- Second shell plate (the "skin" of the hull)
hung on the hull at the bow. Plates covering the hull
from frames 10 to 20 prepped and fit up. Shell
plates prepped for the hull on the port side aft. Work begins on
the same area to starboard. Shell plates cut for frames 76
through 85 on the starboard side.
Week ending January 17, 1997
No report.
Week ending January 24, 1997
- Shell plate hung and fitted between frames 20½
and 29½ on both port and starboard sides.
In this area ABS found the original frames almost pristine and
these are among the few that need not be replaced.
- Bulkhead running across the
width of the hull at frame 64 installed.
- Bulkhead at frame 78 welded, seams sealed and installed.
- Plates cut for replacement of bulkhead 24.
- Work begins to remove the main deck (which carried cars, livestock and
freight) starting on the starboard side aft.
This deck must be entirely replaced.
- Work begins to remove the passenger deck above, also aft.
This deck was planked in wood on steel frames.
Both the wood and steel must be completely replaced.
Week ending January 31, 1997
No report.
Project summary, November 1996 - February 7, 1997
- In mid-November 1996 shipwrights began to
install the steel plates on the lower deck, aft of frame
number 64. This work was finished by mid-December.
The first shell plate was hung on the port side at frames 75
and 85. Since then, workers have installed and welded
four plates on each side of the ship. A new bulkhead has been
installed at frame 64, which forms the aft end of the
engine room. Plates on the lower deck forward of the bulkhead
at frame 36 have been removed and new plates are now
being installed. The
breasthook
has been installed, as well as the replacements for
frames 1 through 5. Bulkheads at frames 8
and 10 have been removed and new bulkheads have
been installed. An inspection of the main deck (which once
carried all the freight) revealed that this deck must be replaced
forward of frame 36 and aft of frame 73. The
original plating, 3/8" thick, was found to measure
only 5/16". Long exposure to the elements after the
NOBSKA was retired in 1973 caused the deterioration.
- ABS review of the new builders' drawings is nearly
complete. ABS has been very helpful getting the NOBSKA
classed to A-1 passenger specifications.
- The second million of a $3 million grant, provided by
the state and federal governments through the Intermodal
Surface Transportation Efficiency Act, came through in
January, and that money is now going into the hull of the ship.
- NESF recently took delivery of another steel order of 64 plates
for the main deck and superstructure later this spring and summer.
Week ending February 14, 1997
- Continued to install new plates on the lower deck forward of frame 36.
- Shell plate hung between frames 30 and 40.
- Bulkhead at frame 93
cut out at the eight-foot waterline level. Will be rebuilt.
- Lower
floor plates
removed aft to gain access to the keel. The entire
keel, running the length of the ship, will be rebuilt.
- The
margin plates
fit up to the bulkhead at frame 64 and partially welded.
Week ending February 21, 1997
No report.
Week ending February 28, 1997
- New keel (the backbone of the ship) installed aft, as the rest
of the keel continues to be rebuilt.
- Bulkhead at frame 93 patched and floor plates
erected from frame 86 to frame 93.
- Two plates fit up on the lower deck forward.
Lower deck welding approximately 60 percent complete.
- Floor plates forward, as well as the breasthook (a
plate fitted just aft of the stern, designed to strengthen the bow)
and a patch at the bulkhead at frame 10 fit up.
- Destructive testing of certain samples of the welding
accomplished and approved by an ABS inspector.
Period ending April 11, 1997
- Work goes forward smoothly with two crews of four men each
working on the framing and plating of the hull, one crew
forward and one aft. The hull has 105 frames, spaced
two feet apart - most of which have been replaced, or will be.
NOBSKA's hull will be covered by 44 new plates, most of
them eight feet wide and 20 feet long.
As of February 1, about 40 percent of the hull work
was finished.
- The lowest and innermost
strake
fitted and welded at the bow,
and 20 feet of new keel installed from the bow aft.
- All the plating on the lower deck (the
engine room deck) installed forward of the bulkhead at
frame 36, and welding completed.
- Framing for the boiler room and engine room (located between
frames 36 and 64) cut and flanged (bent 90 degrees).
- Door in the escape trunk aft at frame 90 installed.
- Framing cut out and awaiting the
installation of the
sterntube
The sterntube arrived April 11.
- The new keel aft installed from the stern frame
(number 105) forward to frame 86.
- Removal of the main deck (the old automobile and freight deck)
continues on the port side from frames 63 to 76.
- All the old steel from the NOBSKA is being sold to scrap
dealers; the foundation recently received a check for $1,200
for scrap metal from the vessel.
- The schedule calls for the hull
work to be finished June 1. The crew will then tear
away the entire superstructure of the vessel, from the main
deck upward, and begin to rebuild it.
- Plans call for critical
components of the machinery (the boiler and condenser, the
turbine generator, the deck winch for the anchors, the diesel
generator set and steering gear) to be ordered by May 1
so that it can be delivered by December 1.
Week ending April 18, 1997
- This week was spent further renewing and strengthening the
framing at the bow to accept a new row of plating (the B strake).
Week ending April 25, 1997
- A very productive week - a new row of plates (the
B strake) installed at the bow on the port side.
- Sterntube readied for installation next week.
- Rebuilding of the main deck (the old automobile, freight and
livestock deck) begins with the installation of the new plates
on the starboard side.
- Framing received for the sections of the hull between
frames 36 and 74. These were cut and flanged at
Washburn and Doughty Shipyard in East Boothbay, Maine.
- All old hull plating now removed from the ship.
Summary through June 23, 1997
- Work continues to go well.
- Both the former freight deck and the engine room deck
completely rebuilt fore and aft.
- Now the effort has turned to
the keel. Two twenty-foot sections of the keel installed from
the stern frame forward to frame 82. At the moment,
work continues on a third twenty-foot section aft of the bow.
- Four plates installed aft between frames 67
and 85, both port and starboard. All framing at the bow
is complete from the stem to the watertight bulkhead at frame
number 10 and from the keel up to the former freight
deck. Shell plates on the C strake installed from the
bow aft to frame 43. Plates on the A
and B strakes completed from the bow to frame 21.
- Sterntube installed and framing around it completed.
|